MAINTAINING FLIGHT OPERATIONS DURING RUNWAY AND TAXIWAY RENOVATION AT NOI BAI INTERNATIONAL AIRPORT

July 1, 2020

The runway and taxiway renovation and upgrading project at Noi Bai International Airport and Tan Son Nhat International Airport, with the Ministry of Transport as the project investor, officially commenced on June 29, 2020. To facilitate construction, the Civil Aviation Authority of Vietnam (CAAV) announced plans to temporarily close runways at the two airports in phases from July 1, 2020, through the end of the year.

The runways will be partially closed in phases to accommodate construction work while ensuring that airport operations are not completely interrupted.

Based on the project's construction phases, the Civil Aviation Authority of Vietnam will adjust flight slots to match the airport's available operating capacity. Overall, the construction work is expected to maintain the airport's daily flight handling capacity. However, to ensure absolute flight safety while construction and flight operations take place simultaneously, hourly flight frequencies will be reduced because aircraft will have to take off and land on the same runway instead of using two separate runways as before.

Accordingly, many flights scheduled during peak hours (6:00–8:00 AM, 12:00–2:00 PM and 4:00–6:00 PM) will be redistributed to off-peak periods.

According to airport statistics, domestic flight operations at Noi Bai International Airport have recovered and grown rapidly, with the airport currently handling an average of more than 450 aircraft movements and 60,000 passengers per day. These figures are expected to increase by approximately 5–10% during July, depending on the day of the week.

Speaking at the groundbreaking ceremony for the runway and taxiway renovation and upgrading project at Noi Bai and Tan Son Nhat International Airports, Mr. Vu The Phiet, General Director of Airports Corporation of Vietnam (ACV), stated:

"The construction process will inevitably have certain impacts on airport operations. However, as the project is being implemented at a time when international flights have not yet resumed due to the COVID-19 pandemic, the extent of disruption will be minimized. ACV is committed to providing strong direction, implementing coordinated solutions and working closely with project management boards, supervision consultants, construction contractors and relevant local authorities to minimize impacts on flight operations while ensuring full compliance with aviation safety and security regulations."

Mr. To Tu Ha, Deputy Director of Noi Bai International Airport, said:

"To proactively respond to potential incidents during the temporary closure of one runway for project construction, Noi Bai International Airport has revised its emergency response, search and rescue, and aircraft removal plans. We have also instructed all relevant teams to strengthen coordination and ensure absolute flight safety."

Mr. Ha also advised passengers:

"During the construction period, passengers should closely monitor flight information provided by their airlines and arrive at the airport at least two hours before departure to complete check-in and other airport procedures, particularly during the peak hours mentioned above."